Crews begin placing rails for Gongbei-Hengqin tracks

(cityofzhuhai.com)

Updated: 2019-06-27

Rails began to be laid on June 25 as major construction of Zhuhai Airport Urban Rail Transit Phase I from Gongbei to Hengqin New Area moved closer toward completion by the end of next month.

All 400-m (437-yd) steel rails will be transported to the construction site by mid-July after being welded at the Honghai Rail Welding Plant, which is administered by China Railway Guangzhou Group. An overhead contact system will be installed as the very next step.

1_副本.jpg

Rails to Hengqin

The urban rail transit project extends the Guangzhou-Zhuhai Intercity MRT. The first phase runs 16.86 km (10 miles) from Intercity MRT Zhuhai Station to Chimelong International Ocean Resort through Wanzai North, Wanzai, Shizimen, Financial Island, and Hengqin Island. The section is expected to pass static acceptance inspection on Aug 31 and become operational on Nov 20.

Meanwhile, the second phase, which runs 23 km (14 miles) from Hengqin to the Zhuhai (Jinwan) Airport, is to be completed by January 2023. Designed with speed of 100 to 160 kmph (62 to 99 mph), the MRT line will cut travel time between Gongbei and the airport to half an hour.

2_副本.jpg

Rail-laying underway [Photos by Chen Lin / Zhuhai Daily]


Related

2018-07-11

Rail line to airport progressing toward 2023 opening

Excavation of the Zhuhai Airport Urban Rail Transit Phase I is nearing completion and planners anticipate static acceptance inspection by year end.

2018-12-21

Gongbei-Hengqin rail line intact and on target for June

Zhuhai Airport Urban Rail Transit Phase I from Gongbei to Hengqin New Area was connected along all 16.9 km (10.5 miles) on Dec 18.

Focus

Xi's Moments
1796761356102795270 (1).jpg Guangdong-Macao In-Depth Cooperation Zone in Hengqin 2 years on
1920-694.jpg 14th China Intl Aviation & Aerospace Exhibition
Copyright © Zhuhai Municipal Government. All rights reserved. Presented by China Daily. 京ICP备13028878号-22