Holiday won't hinder progress on 2nd airport terminal

(cityofzhuhai.com)

Updated: 2021-01-25

The major structure of the new East Airside Concourse has been topped off at Zhuhai (Jinwan) Airport and more than 200 workers will remain on the job throughout Spring Festival.

The contractor says more than half the three-dimensional space truss members will have been hoisted into place by the Feb 11-17 holiday, one year ahead of schedule, and the South and West airside concourses will also have reinforced concrete baseplates in place by then. Half the 4.8-billion-yuan ($743-million) project cost had been expended as of Jan 21.

1.jpg

Major structure of East Airside Concourse topped off [Photo by Chen Xinnian / Guanhai App]

The main terminal building on Central Jinhai Road in Sanzao Town, with two levels underground and four above, will be topped off in October, according to Tang Mingcheng of the China Construction Second Engineering Bureau. The airport will handle 198,000 flights, 27.5 million passengers, and 104,000 tons of cargo and mail annually when the additional terminal opens in June 2023.

With floorage of 190,000 sqm (47 acres), the seabird-shaped T2 will be connected by concourse to Terminal I on its west side. The polygonal cornice will match the current terminal in architectural style and also display images of seabirds, shells, waves, and corollas, said deputy chief engineer Lu Huaying.

Construction of the second terminal encompasses a comprehensive transport hub, aprons, second taxiway, relocated firefighting master station, and isolated aircraft stands.

Currently, the 92,000-sq-m (23-acre) Terminal I is on the brink of designed capacity.


Related

2019-03-20

Design mulled for second terminal at Zhuhai Airport

A second terminal designed for Zhuhai (Jinwan) Airport is given the shape of a seabird, has observation decks for Airshow China, and provides vistas of the sea to the east and mountains between it and Sanzao Town.

2019-07-16

Zhuhai Airport preparing now for escalated capacity

Zhuhai (Jinwan) Airport will be able to handle 198,000 flights, 27.5 million passengers, and 104,000 tons of cargo and mail annually by 2027 when a second terminal and 25 additional aircraft parking stands are in place.

2019-12-03

Work begins on 'seabird' terminal for Zhuhai Airport

Terminal II construction commenced on Nov 29 to increase the overall capacity of Zhuhai (Jinwan) Airport to 27.5 million passengers by 2027.

Join in

64a9430a184ed00c2f309e22.jpg Moving 'Qingming Festival by the Riverside' on exhibition in Zhuhai

Piquing Interest

`.jpg Zhuhai islands aim high in tourism

Living Here

1.jpg Hong Kong-Macao residents guided into living in Zhuhai
Copyright © Zhuhai Municipal Government. All rights reserved. Presented by China Daily. 京ICP备13028878号-22