Hurdles overcome to finish Terminal II basement early

(cityofzhuhai.com)

Updated: 2021-05-07

The basement of the Terminal II main building of Zhuhai (Jinwan) Airport was enclosed two months in advance of schedule during the May Day holiday. The new terminal is to be completed by 2023.

In addition to the threat of seawater encroachment, high requirements were imposed on hoisting height, dust, noise, and lighting in order not to affect the operation of Terminal I west of the construction site. Tang Liang, manager of the airport renovation and expansion project from the China Construction 2nd Engineering Bureau, said these were great challenges at the coastal site.

1.jpg

Construction site of Zhuhai (Jinwan) Airport Terminal II with Terminal I and aircraft at gate in background [Photo courtesy CCTV News App]

With floorage of 187,000 sqm (46 acres), the seabird-shaped Terminal II comprises a main building and east, west, and south airside concourses. Upon completion it will increase the airport's capacity to 27.5 million passengers per year.

Zhuhai (Jinwan) Airport opened in 1995 with a designed capacity of 12 million passengers annually. Its single terminal serves only domestic and regional flights within China. Volume exceeded 10 million in November 2018 and recently reached 11.22 million.

Renovation and expansion commenced in 2019 to meet the surging demands coming with the accelerated construction of the Guangdong-Hong Kong-Macao Greater Bay Area.

 


Related

2019-09-10

Millions budgeted for airport to meet 2027 demands

An allocation of 2.96 billion yuan was approved last week to construct a second terminal and improve facilities to handle 198,000 flights, 27.5 million passengers, and 104,000 tons of cargo and mail annually at Zhuhai (Jinwan) Airport.

2019-12-03

Work begins on 'seabird' terminal for Zhuhai Airport

Terminal II construction commenced on Nov 29 to increase the overall capacity of Zhuhai (Jinwan) Airport to 27.5 million passengers by 2027.

2021-03-25

Work commences on Zhuhai Airport 2nd taxiway, apron

An additional taxiway and apron came under construction March 23 as the building of Terminal II progresses at the south end of Zhuhai (Jinwan) Airport.

Join in

64a9430a184ed00c2f309e22.jpg Moving 'Qingming Festival by the Riverside' on exhibition in Zhuhai

Piquing Interest

`.jpg Zhuhai islands aim high in tourism

Living Here

1.jpg Hong Kong-Macao residents guided into living in Zhuhai
Copyright © Zhuhai Municipal Government. All rights reserved. Presented by China Daily. 京ICP备13028878号-22